Technological map for the construction of prefabricated reinforced concrete sewer wells

The most popular option for constructing a sewer well, of any type, is concrete rings. These simple and uncomplicated reinforced concrete products have been holding the bar for many years. They are used in the creation of domestic, storm and drainage sewers, and collectors.

Due to their high performance properties, they can be used in any climatic zones of the country. A well made of concrete rings has many advantages, but it is not without its disadvantages. Also, there are some nuances that should be taken into account when choosing and installing them.

SECTION III. ORGANIZATION AND TECHNOLOGY OF THE CONSTRUCTION PROCESS

1. Before starting work on constructing wells, the following must be done:

— make a breakdown of well construction sites;

— clear the area of ​​forest, bushes, etc.

— demolish or move buildings and structures from the construction site;

— build temporary roads or exits from permanent roads to service construction.

2. Transportation of reinforced concrete well elements and other building materials (mortar, cement, reinforcement) to well construction sites is carried out by trucks with trailers from the supply bases of construction and installation organizations.

3. The construction of wells is carried out in the following sequence;

— development of a pit;

— cleaning the bottom of the pit, checking that the bottom marks and the steepness of the slopes comply with the design;

— treatment of the base for wells with tar or bitumen materials to a depth of at least 0.2 m with careful compaction;

— concrete preparation device;

— installation of a concrete tray, reinforced with horizontal reinforcing mesh, and sealing of the ends of the incoming and outgoing pipes;

— insulation of the inner surface of reinforced concrete rings with bitumen mastic;

— installation of prefabricated reinforced concrete well elements;

— grouting the seams between the well elements with cement mortar;

- cement plaster and iron tray;

— backfilling the well with soil with careful compaction and installation of a waterproof lock on the pipe entries;

— installation of a concrete blind area around the neck of the well 1.5 m wide;

— insulation of the joints of the reinforced concrete rings of the well with hot bitumen over a primer;

— well testing (after completion of construction of the sewer network section).

Due to the fact that pits for wells are being developed simultaneously with trenches, issues of excavation work are not considered in this technological map. In calculating the costs of constructing wells, only the amount of excavation work that is associated with widening the trenches in the places where the wells are installed is taken into account.

CONSTRUCTION OF WELLS

1. Preparation of the foundations for wells is carried out as earthworks are completed at the site.

2. A preparation of 100 mm thick M-50 concrete is laid on the base.

3. The reinforcement mesh of the tray base is laid on the concrete preparation, the incoming and outgoing pipelines are installed in the design position and a tray made of M-100 concrete is installed.

4. After the concrete tray has acquired the required strength, the prefabricated reinforced concrete elements of the well are installed using a truck crane.

5. For slinging the elements, a four-leg sling with a lifting capacity of 2.0 tons is used.

6. All elements of the well are installed on M-50 cement mortar.

7. The construction of a clay castle is carried out after sealing the pipelines in the walls of the well. The width of the clay castle is taken to be 300 mm, and the height is 600 mm greater than the outer diameter of the pipelines connected to the well.

Well test

Wells of free-flow pipelines with internal waterproofing are tested for density by determining water leakage.

Testing of wells can be carried out either together with pipelines or separately. Before filling wells and trenches with soil, a preliminary test is carried out, and after filling, a final test is carried out.

Wells are tested for density no earlier than 24 hours after they are filled with water. Hydraulic pressure in a well in a leak test is created by filling the well to the top with water.

Wells are considered to have passed the preliminary test if no visible water leaks are detected during inspection. The amount of leakage should be determined by the volume of water added to the well to the original level during the test time, which should last at least 30 minutes. In this case, a decrease in the water level in the well is allowed no more than 20 cm. The well is recognized as having passed the final density test if the leakage or inflow determined during the test is equal to 60 l/day or less than this value.

Backfilling of trenches and pits

After testing the wells and pipelines, the well pits and trenches are backfilled layer by layer with soil using a bulldozer. Soil compaction is carried out using pneumatic rammers.

Selection of reinforced concrete rings

The issue related to the choice of reinforced concrete rings should be resolved responsibly. It is recommended to purchase material after carefully studying all the characteristics of these products and making the necessary calculations. It is important that there is no damage to their surface, including cracks or holes. Otherwise, the rings will be subject to rapid destruction during operation.

Rust on mounting loops protruding on the surface of concrete products is unacceptable. If it is present, then this is evidence of a corrosion process. As a result, lifting the product without breaking the loop will be impossible. When purchasing a high-quality workpiece, you need to check the availability of a passport containing information about the constituent materials.

The lining of reinforced concrete rings provides reliable protection of products from rust. It allows for high-quality reconstruction of reinforced concrete wells from the inside. If the sewer begins to collapse, starting from the tank, then this process can only be prevented with the help of a lining. It is a modern polymer protection that ensures the long service life of concrete rings.

The use of polyethylene sheets for lining helps prevent the formation of all kinds of growths on the walls of the well from the inside. The sealed surface can be easily cleaned if necessary. This helps to improve the operational characteristics of structures.

SECTION IV. AND METHODS OF LABOR WORKERS

Work prior to the construction of sewer wells is carried out by four specialized units: concrete workers, pipe layers, insulators and bulldozer operators.

The composition of units by profession and the work they perform are shown in the table.

No. of linksTeam composition by professionQtyList of works
1Concrete worker - 4 rubles. Concrete worker - 2 rubles. 1 1Installation of concrete preparation and trays Plastering of trays Installation of concrete blind area.
2Pipelayers 4 r.2Completion of the pit manually. Checking the elevation of the pit bottom and the steepness of the slopes. Construction of foundations for wells. Installation of well and neck elements with sealing of seams and grouting of the surface with cement mortar. Well test. Soil compaction when filling a well.
Pipelayers 3 r.2
Pipelayers 1 r.1
Truck crane operator 5 r.1
3Insulator 3 r.1Heating bitumen in a mobile boiler. Cleaning and painting the inner surface of the rings with bitumen.
Insulator 2 r.1
4Bulldozer driver 5 r.1Backfilling the well pit with soil.
TOTAL:11 people

The placement of equipment, devices and tools in the work area during the installation of wells is shown in the work flow diagram.

SEQUENCE OF WORK EXECUTION

No. pp.Process nameSequence of work operations
1.Well construction.Cleaning slopes and pit bottom. Mixing the soil at the base of the well with bitumen or tar materials. Soil compaction. Concrete preparation device for a well made of M-50 concrete. Installation of reinforcing mesh. Construction of a concrete tray M-100. Insulation on the edge of the pit with hot bitumen of the inner surface of the rings. Installation of well and neck elements. Grouting of joints with ironing and coating with hot bitumen.
2.Well testPreliminary test of the well with water (before backfilling the pit). Elimination of defects. Final testing of wells (after backfilling the pit).
3.Backfilling of pits and trenches.Filling well pits with soil (after testing the wells). Compacting soil with pneumatic rammers. Construction of a concrete blind area around the well neck.

Classification of wells

They are divided into two types:

  • Sewer. They are necessary for the drainage of storm and wastewater.
  • Water collection. Their name “speaks for itself.”

The difference between these two types lies in their operational characteristics, sizes and methods of arrangement. In turn, water-collecting reinforced reinforced concrete structures can be:

  • Mine.
  • Made in the form of a well.

And sewer wells can be:

  • Or a septic tank with one or more chambers.
  • Or a drain hole.

In our article we will dwell in detail on the arrangement of a water well.

METHODS AND TECHNIQUES OF WORK

The installation of concrete preparation and trays is carried out by unit No. 1 of the following composition:

concrete worker 4 r. — 1 person (1) link;

concrete worker 2 r. — 1 person (2).

The concrete mixture delivered to the well installation site is supplied by the concrete worker (2) to the laying site along a wooden tray. A concrete worker (1) located in the pit places concrete at the base of the well and compacts it using a hand tamper.

After the concrete preparation is installed, a reinforcing mesh is laid on it and the tray is concreted. Cleaning the bottom and slopes of the pit, preparing the base for the well, sealing the pipes in the tray and installing the well elements is carried out by unit No. 2 of the following composition:

truck crane operator 5 r. — 1 person (1)

pipe layer 4 r. — 1 person (2) link

pipe layer 4 r. — 1 person (3)

pipe layer 3 r. — 2 people (4;5)

pipe layer 2 r. — 1 person (6).

Before starting work on constructing a well, the pipelayer (4) cleans the slopes and bottom of the pit, checks compliance with the design of the bottom elevation and the steepness of the slopes of the pit.

Pipelayers (6 and 5) are busy working to saturate the soil at the base of the well with bitumen. The loosened and bitumen-impregnated soil is leveled and compacted using hand tampers.

Pipelayers (2 and 3) are busy preparing for the installation of reinforced concrete rings of the well, sealing pipelines into the tray, installing the well rings and installing a clay castle at the junction of the pipelines with the tray.

Arrangement of workers during the installation of wells: the pipe layer (5) is at the top and is engaged in slinging loads, the pipe layers (2 and 3) are installing the well elements in the pit, the pipe layer (4) is preparing the bases of the wells for installation and grouting the seams of the mounted well elements, and the pipe layer (6) - for auxiliary work (cleaning the reinforced concrete rings of the well from contamination, carrying materials, tools, etc.).

The pipe layer (5), having secured the lower ring of the well with a four-legged sling, gives a signal to the crane operator to lift the load. After a test lift to a height of 0.1-0.2 m above ground level, the pipe layer (5) checks the reliability of the sling and allows the ring to be delivered to its installation site. Pipelayers (2 and 3), having accepted the reinforced concrete ring of the well, install it on the tray with mortar. After verifying that the ring is installed correctly, it is unslinged and a signal is given to the link members to remove the slings and prepare for the installation of the next ring.

The cement mortar protruding from under the rings (during their installation) is removed, and the seam is thoroughly rubbed inside and outside the well. The correct installation of the rings is checked by level and plumb. The final well installation operations are the installation of the hatch (cage and cover) with the sealing of the cage on the neck with M-50 cement mortar and the installation of a clay castle.

Insulation of reinforced concrete well rings with bitumen is carried out by unit No. 3, consisting of two insulators of the third (1) and second (2) categories.

The insulator (2) heats the bitumen in a mobile boiler, and the insulator (1) prepares the reinforced concrete rings for insulation (cleaning off contaminants, applying a primer, etc.).

After the primer has dried, insulators (1 and 2) use brushes to apply hot bitumen to the inner surface of the rings at a distance of 5 cm from the edges.

After installing the well rings and sealing the joints, insulators (1 and 2) prime the joints and apply bitumen to them.

Hydraulic testing of the well is carried out by link No. 2 by filling it with water and observing its leakage. A preliminary test is carried out before filling the well with soil and is aimed at identifying visible water leaks, and the final test is to determine the amount of leakage, which should not exceed 60 l/day for a given well.

The well is filled with soil in layers using a bulldozer. Each layer is compacted by a pipe layer (4) using a pneumatic rammer.

The completion of the well construction is the installation of a concrete blind area around the neck. The concrete blind area is arranged by the concrete workers of unit No. 1 in the following order: the concrete worker (2) scatters crushed stone around the neck and then compacts it, and the concrete worker (1) lays concrete on the prepared base and levels it.

Schedule for the construction of prefabricated reinforced concrete wells with a diameter of 1.0 m and a depth of 3.0 m on sewer networks

Note. The labor costs of the truck crane operator are not taken into account in the schedule.

SAFETY

Work in excavations with slopes that have been moistened after soil removal is permitted provided that precautions are taken against soil collapse, namely:

a) a thorough inspection by the workman or foreman before the start of each change in the condition of the soil and its artificial collapse in places where “peaks” and cracks are found at the edges and on the slopes;

b) temporary cessation of work in the excavation until the soil is drained if there is a danger of a collapse;

c) local reduction of the steepness of the slope in areas where work in the excavation is urgent;

d) prohibition of the movement of vehicles and mechanisms within the collapse prism.

When installing a well, a person from among the engineering and technical personnel must be appointed, responsible for the safe execution of work on moving and installing loads with cranes.

All lifting mechanisms and devices (crane, slings) must be periodically checked before starting operation, as well as during operation, in accordance with the rules of Gosgortekhnadzor.

When installing well elements, the edges must work on outriggers. The lifting capacity of the slings must correspond to the weight of the load being lifted. Lifting and moving well elements should only be done after checking the correctness and reliability of their slinging. When lifting, moving and lowering the well elements with a crane, it is prohibited for people to remain in the area of ​​its operation; the well elements must not be allowed to be moved above the pipelayers’ workplace. The supplied well element should be lowered above the place of its installation by no more than 30 cm, and only from this position the pipelayers direct it to the design position.

Workers who are at least 18 years old, who have passed a medical examination and trained according to a special program approved by Gosgortekhnadzor and certified by the qualification commission with the issuance of certificates, are allowed to work as a sling operator.

Unslinging the installed well elements is allowed only after they have been firmly and securely fastened. It is prohibited to swing a suspended load and leave it hanging without supervision, as well as to carry out installation in a wind force of more than 6 points.

The operation of a jib crane near power lines is permitted only if the horizontal distance between the extreme point of the mechanism, cargo ropes (cables) or load (at the greatest reach of the working body) and the nearest power line wire is not less than that specified in Table 1.

Permissible horizontal distance from operating machines to power cables

Table 1.

Transmission line voltage in kV.up to 11-2035-110154220330-500
Distance in m1,524569

When moving a jib crane, as well as when transporting well elements under the wires of existing power lines, the vertical distance between the highest point of the machine and load being moved and the lowest point of sagging of the wire must be no less than that specified in Table 2.

Permissible vertical distance from the equipment being moved to power cables

Table 2.

Transmission line voltage in kV.up to 11-2035-110154-200330500
Distance in m123456

Subject to the above breaks, work can be carried out if there is written permission from the electricity supply organization to carry out work in the security zone and if the crane operator has a work permit signed by the chief engineer of the SUM. This work must be carried out under the direct supervision of an engineer and technical worker appointed by order and having permission from the State Mining and Technical Supervision Authority.

Loading of rigging equipment exceeding that for which this equipment is approved for operation is not allowed.

Loads must be slinged according to pre-developed schemes.

Lifting loads covered with earth, snow or frozen to the ground is not allowed. It is prohibited to pull (drag) loads with lifting mechanisms by slanting ropes or turning the boom.

It is strictly forbidden to leave lifted loads suspended. Removing hooks from lowered structures is permitted only after installing them in the design position. Moving structures after their installation and removal of gripping devices is prohibited.

The mortar under the installed structures must be laid before the structure is delivered to the place of its installation.

Heating bitumen within wells, trenches and other cramped places is prohibited. Due to the fact that hot bitumen can cause burns if it comes into contact with the human body, even if covered with ordinary cotton fabric, workers must be provided with the following protective clothing and footwear:

a) canvas jackets and trousers (trousers must be wide and worn over the shoulder);

b) leather shoes or boots;

c) canvas mittens:

d) glasses with simple lenses to protect the eyes from accidental splashes of hot mastic.

Overalls must always be in perfect working order. Work without a full set of overalls and shoes is not permitted.

1. Basic materials and products.

No. pp.Name of materialsGOST brandUnit change Quantity
1.Support ringKO GOST 8020-56PC.1
2.Adjustment stonesKR GOST 8020-56PC.6
3.Neck ringsK-7-3 GOST 8020-56PC.2
4.Floor slabP-10 GOST 8020-56PC.1
5.RingsK-10-9 GOST 8020-56PC.2
6.LukeTU-264-55PC.1
7.Cement mortarM-50m30,06
8.ConcreteM-50m30,33
9.ConcreteM-100m30,55
10.Bitumenkg49
11.Petrolkg3,2
12.Reinforcing meshPC.1
13.Crushed stonem30,22

Machinery, equipment and power tools.

No. pp.NameTypeBrandQuantity
1Automotive craneLAZ-6901
2BulldozerD-159.B1
3CompressorPKS-51
4Pneumatic rammersI-1571

Inventory and devices.

NameUnit change Quantity
1234
1.Cross sawsPC.1
2.Bayonet shovelsPC.4
3.Steel crowbarsPC.2
4.Picking shovelsPC.3
5.Bench hammersPC.2
6.Tape measures 10 mPC.1
7.Folding meterPC.2
8.Metal levelPC.2
9.Metal plumb linePC.1
10.Bench chiselsPC.5
11.AxesPC.2
12.Adjustable wrenchesPC.2
13.Opening forkPC.1
14.Mobile container for cementPC.1
15.Universal sling with a lifting capacity of 2.0 tons.PC.2
16.Four-legged sling with a lifting capacity of 4 tons.PC.2
17.Mobile boiler for heating bitumenPC.1
18.Inventory plugs for hydraulic testingPC.6
19.StairsPC.3
20.Transitional bridgesPC.2
21.LevelPC.1
22.Leveling slatsPC.2
23.Template for tray arrangementPC.1
24.Wooden tray 3.5 m long.PC.1
25.Mason's TrowelsPC.2
26.Plastering trowelsPC.2
27.BucketsPC.4
28.Mortar boxPC.2
29.BrushesPC.5
30.Manual tampingPC.1

Preparatory stage of arrangement of reinforced concrete concrete structures

We carry out the following work:

  • We determine the location where the well will be installed. There are several methods: using frames, based on geodetic surveys and electrical-vertical sounding. It is best to use all methods together.

On a note! The optimal time for constructing a well is August-September. They are also dug in winter, after 3 weeks of frost, when the upper layers of the soil freeze and they do not recharge the aquifer.

  • We clear the area from bushes, trees, garbage and old buildings.
  • We select the type and size of reinforced concrete rings (RCR), and also calculate their number.
  • If necessary, we arrange temporary access roads for lifting equipment that delivers the necessary materials, as well as digging a pit (if you decide to drill a mine using a mechanized method).

Important! We do not recommend turning (that is, rolling) reinforced concrete rings over long distances. This is fraught with the fact that chips and cracks may form on the surface of the product.

How to properly place a septic tank and filter structures on the site

Requirements for the placement of treatment facilities and soil filtration structures that complement them are contained in various SNiPs, SPs, SanPiNs. Moreover, there are discrepancies in the numbers between the standards. However, some definite recommendations can be made:

  • The septic tank must be located at least 5 m from the house. And from the border with the neighboring plot - at least 1 m. If neighbors live on the plot, then it is advisable to increase this distance to 4 m or more.
  • The filter well is located no closer than 8 m from the house. Filtration fields with a capacity of up to 15 m³/day - no closer than 15 m from the house.
  • The minimum distance from the treatment and filtering facility to the water supply source (well or borehole) is 15 m if the structures are located against the flow of groundwater. Or 30 m, if downstream.
  • The distance between the septic tank and the reservoir is determined in each specific case individually depending on the category of the reservoir, its size, etc.
  • The distance between the treatment plant and the underground gas pipeline depends on the pressure in it. If the pressure is low (not higher than 0.005 MPa), then this distance should be at least 1 m (according to SP 62.13330.2011 * “Gas distribution systems. Updated edition of SNiP 42-01-2002”, table B.1).

Often in villages there are internal standards for the placement of treatment facilities, and then you need to focus on them.

In addition, it is worth assessing the terrain of the site:

  • Treatment and filtering facilities are located lower in relief relative to the source of water supply, so that the flow of groundwater is not directed away from them towards the well or well.
  • If possible, the treatment plant is installed at a point on the site where it will not be flooded with melt water in the spring.

Disadvantages of SRC

  • Great care is required when installing the well structure. No distortion is allowed. Otherwise, there is a high probability that the ring will burst (and it’s good if it is the top part, otherwise you will have to spend a lot of time dismantling the already mounted elements).
  • The large weight of the well rings is also considered one of its disadvantages. For example, one product with a diameter of 1.0 meter weighs about 600 kilograms. That is why loading/unloading and installation will most likely require special equipment.

Materials

Before you start building a sewer well, you need to select the materials that will be required to create it.

The design of a sewer well made of concrete rings includes:

  • pipes (PVC pipes for outdoor use are suitable, as a rule, they are brown/orange);
  • fittings and plugs;
  • prefabricated reinforced concrete products.

Reinforced concrete includes:

  • rings made of concrete mixture (most often KS rings are used, they can be either with or without a lock);
  • lids (their shape can be any, the main thing is that the size matches the diameter of the ring);
  • bottom (you can buy a ready-made one, or you can make a pillow from a concrete mixture yourself).

After we have decided on the location and selected all the necessary materials, we begin to build the septic tank.

Sewage well diagram


Septic tank diagram

Scheme:

  1. Sewage water is purified in the first tank (the first stage of purification). A sediment forms at the bottom, which is removed using a pump. This cleansing process is carried out, as a rule, once a year (sometimes less often).
  2. Second stage of cleaning. The wastewater is cleaned again in another container. As a result, dirt and impurities settle to the bottom.
  3. With the help of a drainage structure, the wastewater is completely cleaned. The sewer liquid is absorbed into the soil layer after it passes through the crushed stone. Sometimes it happens that the water layer is high, the absorption process will be slower. In this case, the liquid is pumped out with a pump.
Rating
( 1 rating, average 5 out of 5 )
Did you like the article? Share with friends:
For any suggestions regarding the site: [email protected]
Для любых предложений по сайту: [email protected]